The design/build approach maintains a balance between design and construction so your best interest is achieved. We will match you with an architect who is experienced in your type of construction. As your partner in this process, Borton Construction is responsible to keep your project on budget and on schedule. It is our goal to exceed your expectations.
| DESIGN/BID/CONSTRUCT |
DESIGN/BUILD |
| Contractural Relationship Selection |
| Architect/ Engineer selected by Owner |
Design/ Build team of Architect/ Engineer and Contractor selected by Owner |
| Contractor selected by bidding |
|
| Contractural Relationship Agreements |
| Architect/ Engineer + Owner |
Architect/ Engineer + Owner |
| Contractor + Owner |
Contractor + Owner |
| Budget Cost Estimates |
By Architect/ Engineer at each phase (Low Accuracy) |
By Contractor at each phase (Higher Accuracy) |
| Budget GMP |
| Not available by Architect/ Engineer firm |
Available at design development phase |
| Budget Bidding |
| 100% competitive bid |
70-80% competitive bid |
| Construction Administration |
| Construction documents compliance monitored by Architect/ Engineer |
Construction documents compliance monitored by Architect/ Engineer |
| Construction Payments |
| Certified by Architect/ Engineer |
Certified by Architect/ Engineer |
| Construction Savings |
| Savings realized at bid time |
Savings realized throughout the construction |
| Advantages |
| Traditional defined roles |
Single point of responsibility |
| Easily understood process |
Builder's input during design |
| Owner actively participates in design process |
Owner actively participates during design and construction |
| Bid on complete documents |
Guaranteed maximum price budget established early on |
| Unbiased contractor selection |
Allows for fast track construction |
|
Reduced change orders |
|
Allows for partnering the right architect with the right contractor |
|
Increased owner involvement in critical decisions |
|
Contractor involves subcontractors experienced with Design/ Build |
| Disadvantages |
| More lengthy process |
Guaranteed maximum price is not based on final design |
| Cost of construction not firm |
Contractor and architect must be experienced in Design/ Build |
| Adversarial relationship more likely |
Smaller quantity of subcontractors qualified for Design/ Build |
| More change orders/ unexpected costs |
|
| Lower owner participation during construction |
|
| Low bid is not always qualified bid |
|